The slotbot is basically done. All that's left is manufacturing the parts and putting it all together. The bullet is fully extended out to open the flipper in this picture.
This site will be used for team project done for Mechanical Engineering 250. We, team 'Shoelace', will be designing a robot for Slotgame.
Monday, November 29, 2010
completed slotbot design
The slotbot is basically done. All that's left is manufacturing the parts and putting it all together. The bullet is fully extended out to open the flipper in this picture.
constraints
Tuesday, November 23, 2010
Monday, November 22, 2010
Bill of Materials
The bill of materials needed for MS8 are saved as a google doc. Here is the link:
https://docs.google.com/leaf?id=0By22PtzkcSjeNzBiZTVhMzItMjU3OC00YWZjLWJmN2MtYTcwMTA1NTExZjEz&authkey=CIzJrI8D&hl=en
https://docs.google.com/leaf?id=0By22PtzkcSjeNzBiZTVhMzItMjU3OC00YWZjLWJmN2MtYTcwMTA1NTExZjEz&authkey=CIzJrI8D&hl=en
Schedule
Our schedule for the semester has been on our ctools site. The link for the excel file is https://docs.google.com/leaf?id=0By22PtzkcSjeNmRlMWEzMDQtMjAzNS00Y2FkLTlhNmUtYWZjYTI5MTU2MGYz&sort=name&layout=list&num=50
Sunday, November 21, 2010
Meeting Minutes Sun. Nov 21 2010
We met at Mojo CLC from 5 PM to finalize our plans for MS 7 and MS 8 due before the Thanksgiving break.
Last friday(two days ago), we finished manufacturing 1 tensioner, rollers(1 gear, 1 drive, 2 normal), and 4 angle stock.
Tomorrow(Mon), in the machine shop, we will be using the Lathe #3 from noon to 2PM. We will finish rack axle, motor plate, bullet, barrel, and spring plates.
Last friday(two days ago), we finished manufacturing 1 tensioner, rollers(1 gear, 1 drive, 2 normal), and 4 angle stock.
Tomorrow(Mon), in the machine shop, we will be using the Lathe #3 from noon to 2PM. We will finish rack axle, motor plate, bullet, barrel, and spring plates.
Thursday, November 18, 2010
Lab Times This Week
Howdy boys,
We have reserved time in the workshop for today (Thursday) from 6pm-8pm and Friday 11:30-2pm. We also signed up for the water cutter on Wednesday of next week. The parts arrived at my house today and we should be able to make nearly all of of major components before break. See you guys tonight!
Andrew
We have reserved time in the workshop for today (Thursday) from 6pm-8pm and Friday 11:30-2pm. We also signed up for the water cutter on Wednesday of next week. The parts arrived at my house today and we should be able to make nearly all of of major components before break. See you guys tonight!
Andrew
Tuesday, November 16, 2010
Meeting Nov. 15 2010
Today in class, we built the rest of the gear boxes. And the gun and barrel designs were more specified. After talking with Davor, we made the gun more practical.
In the evening meeting at Mojo from 6 PM, we studied for the Midterm on the following day.
Good luck on your/my Midterm!
In the evening meeting at Mojo from 6 PM, we studied for the Midterm on the following day.
Good luck on your/my Midterm!
Saturday, November 13, 2010
Meeting on Nov.13
We had team meeting from 5 pm to 8 pm to discuss about the gun design specifications and to order materials necessary for further manufacturing.
Wednesday, November 10, 2010
Schedule for the Rest of the Week
Wednesday: Meet to finalize ALL aspects of design. (i.e. couplings, gears, mounts, motors)
Complete the homework questions possible without us completely finishing lab.
Thursday: Finish last part of motor lab, complete number one of homework.
Friday: Rise and shine, we're meeting at the workshop at 11:30am until 2:00pm to construct the motor mountings and reinforcement block for the conveyer. We can also begin to reinforce the racks with some aluminum backing.
Saturday: Go Blue! Shoelace for Heisman!
Sunday: Trip to the hardware and scrap metal stores. We need to purchase parts and order whatever we can't find in the store.